top of page
Search


Hans
Oct 13, 2020
SIDING, RAILING AND BUILT-IN GRILL
Lots of work was done last two weeks. Cedar shingle siding, stainless steel cable railing, and stone island with built-in stainless steel...


Hans
Sep 19, 2020
Windows and exterior Doors
Along with the windows and doors all exterior trim was done as well. Sheetrock is done, and a mason starts stone veneer for the grille...


Hans
Sep 7, 2020
IPE Deck
IPE deck is finished, some exterior PVC trim is installed, and existing blue stone was used for a walk. Windows and exterior door will be...


Hans
Aug 20, 2020
Framing
Framing is done and the structure is starting to get a shape.


Hans
Aug 13, 2020
Floor slabs and first sill plates
This week, a door opening was saw cut into the existing foundation wall. A new slab was poured in level with the existing basement floor,...


Hans
Aug 1, 2020
Foundation walls
Foundation walls and footing drains where inspected today. The contractor used drainage membrane to protect asphalt waterproofing. Back...


Hans
Jul 30, 2020
Footings and underpinning
New footings were poured one week after excavation. The underpinning was done in one shot about 8', instead of 3' sections. The inspector...


Hans
Jul 18, 2020
Excavation
We finally got permit and the general contractor CADCO CORP was able to start. Excavation was done in few hours.


Hans
Jun 16, 2020
Farmhouse Addition - Final design
The final design can be seen here - https://www.hanscadek.com/residential-harding-addition. HCA represented the project at Zoning Board...
bottom of page