HansOct 13, 2020SIDING, RAILING AND BUILT-IN GRILLLots of work was done last two weeks. Cedar shingle siding, stainless steel cable railing, and stone island with built-in stainless steel...
HansSep 19, 2020Windows and exterior DoorsAlong with the windows and doors all exterior trim was done as well. Sheetrock is done, and a mason starts stone veneer for the grille...
HansSep 7, 2020IPE DeckIPE deck is finished, some exterior PVC trim is installed, and existing blue stone was used for a walk. Windows and exterior door will be...
HansAug 13, 2020Floor slabs and first sill platesThis week, a door opening was saw cut into the existing foundation wall. A new slab was poured in level with the existing basement floor,...
HansAug 1, 2020Foundation wallsFoundation walls and footing drains where inspected today. The contractor used drainage membrane to protect asphalt waterproofing. Back...
HansJul 30, 2020Footings and underpinningNew footings were poured one week after excavation. The underpinning was done in one shot about 8', instead of 3' sections. The inspector...
HansJul 18, 2020Excavation We finally got permit and the general contractor CADCO CORP was able to start. Excavation was done in few hours.
HansJun 16, 2020Farmhouse Addition - Final designThe final design can be seen here - https://www.hanscadek.com/residential-harding-addition. HCA represented the project at Zoning Board...