Hans
Jun 15, 2020
Rumore Residence - Plumbing and HVAC
Thanks to a truss system floors the plumbing pipes and HVAC ducts are hidden in the floor. No soffit or partially dropped ceiling in the...
Hans
Jun 15, 2020
Roofing and Vapor barrier
Whole house was wrapped with vapor barrier, and roof was done as well. Black asphalt shingle roof with black flashing and trims. Sleeves...
Hans
Jun 15, 2020
Rumore Residence - Framing
Complete framing took only 5 days. Everyone where surprised how precised the SIPs panels and trusses are. #hanscadekarchitecture...
Hans
Jun 15, 2020
Rumore Residence - House on the truck
All walls, floors and roof are made in a manufacture off-site and delivered on the truck. Exterior walls are Structurally insulated...
Hans
Jun 15, 2020
Rumore Residence - Foundation walls
Forms are ready for concrete! All sleeves for utilities are in place, no later drilling needed. Part of the basement walls is fully...
Hans
Jun 15, 2020
Rumore Residence - Excavation
The soil was soft and the excavation went fast. Since the site is in hill they didn't have to go to deep. On the other hand, because of...
Hans
Jun 15, 2020
Rumore Residence - Site preparation
I started this blog little bit late. At this moment the framing is already done. Anyway, I promise from now on I will be up to date!...